1997
4th December: Wind measurements commence.
2004
8th May: Advance notification sent.
2005
Licence application sent. Midtfjellet Vindkraft founded.
2006
Actual project planning commences.
2008
28th May: License granted.
2010
Enova provides support for half the project.
2011
6th April: Investment support verified by ESA.
5th September: Construction phase commences.
2013

1st June: Phase I put into operation.
17th September: Wind park officially opened at 11 a.m. alongside turbine no.7.
1st December Phase II put into operation.
2014
Operating phase.
Midtfjellet Day organised.
2016

June: Half-marathon organised.
2017
May: Investment decision phase III.
June: Construction phase commences.
2018

10th August: Phase III put into operation.
October: Commissioning.