Third phase put into operation on 10th August 2018
Phase III consists of 11 new turbines of type Nordex N117/3600 and a little under 3 km of road from the new turbine site to the existing road network. The current road infrastructure and transformer wwere used for phase III.
The detailed location of the new turbines and phase III approval by NVE can be found here:
A little technical information,
The wind turbines are of type Nordex 117/3600 – TS91. hat is to say that the turbine is 91 metres high to the centre of the rotor. The rotor’s diameter is 117 metres. Each turbine produces 3600 KWh per hour at full production. Total phase III production amounts to 39.6 MW.
Click on the picture below to view our development milestones: